May 10, 2010

First delivery

The first equipment has arrived at the building.  We purchased a grinder, a slicer, a retail case, and three scales from an equipment distributor in Hermosillo, Sonora.
IMG_2331
Here are the delivery men unloading the equipment.
IMG_2328
The old adobe wall that runs along one side of the production room has been redone with new cement plaster, paint, and sealer.  Here is a “before” picture.
DSC_3307
Here is the “after” picture.
IMG_2358
We have finished installing the three insulated doors that were purchased from a used equipment dealer.  Here is the door to the product cooler.
IMG_2355
Here is the front door, which leads from the non-refrigerated loading dock to the refrigerated production room.
IMG_2367
Here is the back door that leads from the production room to the smokehouse room.
IMG_2370